Today.Az » Business » Shah Deniz Project continued to progress according to schedule
07 May 2006 [13:00] - Today.Az
The Shah Deniz gas and condensate development project has continued to progress according to schedule since the beginning of 2006.

Stage 1 construction is currently 93% complete overall, AzerTAg informs.

During the first quarter of 2006 the project spent $288 million of the $865 million planned 2006 capital expenditure budget.



Copyright © Today.Az