Today.Az » Business » First two power units of Nakhchivan Gas-Turbine Power Plant connected to tension
25 April 2006 [08:12] - Today.Az
The first and second power units of the Nakhchivan Gas-Turbine Power Plant have already been connected to the tension.

As APA informs quoting the chief of the Nakhchivan Energy Office Yasin Seferov, about 3 mn kWh of electricity is consumed in Nakhchivan AR during the day and 420 thousand kWh of it fall to share of the Nakhchivan Gas-Turbine Power Plant.

At present the Enerco Company (Germany), GTT Group of Companies (Italy) and ABB Company (Austria) are implementing final completion works for connecting the third and fourth power units to the network: "So, other power units will be connected to the tension by the end of this month and about 1 mn kWh of electricity will be produced in the power plant."